CompTIA Project+ 認定 PK0-400 試験問題:
1. A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable.
Which of the following factors will MOST likely influence the communication methods used in the project?
A) Technological factors
B) Cultural differences
C) Language barriers
D) Personal preferences
2. During the execution phase of a project, a project task has run longer than anticipated.
Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
A) 16 days
B) 14 days
C) 19 days
D) 12 days
3. A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.
Which of the following documents should the project team reference to fast-track the project? (Choose two.)
A) Network diagram
B) Project schedule
C) Configuration management plan
D) Project plan
E) Scope management plan
4. A milestone task on the critical path has been completed.
Which of the following should the project manager notify?
A) Project sponsor
B) Owner of predecessor task
C) Project steering committee
D) Project team
5. A project requires daily status updates.
Which of the following is the MOST effective method for providing these updates?
A) Kickoff
B) Standup
C) Backlog
D) Retrospective
質問と回答:
| 質問 # 1 正解: A | 質問 # 2 正解: D | 質問 # 3 正解: A、B | 質問 # 4 正解: A | 質問 # 5 正解: B |














1151 お客様のコメント
品質保証JPexamはIT認定試験のシラバスに従って、試験問題の範囲を正確に絞って、的中率が99%の最新問題集を捧げます。
1年間の無料更新サービスJPexamは1年以内に問題集の無料更新サービスを提供し、お客様がいつでも最新版の問題集を持つことを保証いたします。もし試験の内容が変更されたら、弊社は直ちにお客様にお知らせします。それに、弊社の問題集が更新されたら、早速メールで最新バージョンを送付いたします。
全額返金JPexamの問題集を利用すると、短時間で勉強しても試験に合格できるのを保証いたします。試験に不合格になってしまった場合、弊社は全額返金いたします。(
ご購入前のお試しJPexamは問題集のサンプルを無料で提供いたします。ご購入前にサンプルを試用して製品の品質を確認することができます。ご遠慮なく利用してください。