Adobe AD0-E911 試験概要:
| 認定ベンダー: | Adobe |
|---|---|
| 試験名: | Adobe Workfront Project Manager Certified Professional |
| 試験番号: | AD0-E911 |
| 出題数: | 50 |
| 合格点: | 33/50 |
| 対応言語: | 英語 |
| 試験時間: | 100 分 |
| 試験形式: | オンライン監視付き試験, 多肢選択式, シナリオベース問題 |
| 受験料: | $125 USD (グローバル) / $95 USD (インド) |
| 関連資格: | Adobe Workfront Core Developer Professional Adobe Experience Cloud certifications |
| 推奨トレーニング: | Adobe Experience League - Workfront ラーニングパス |
| 受験申し込み: | Adobe 認定ポータル |
| サンプル問題: | Adobe AD0-E911 サンプル問題 |
| 受験方法: | オンライン監視付き試験(リモート、カメラ必須) |
| 前提条件: | Adobe Workfront またはプロジェクト/業務管理ツールの使用経験が6〜12ヶ月あることを推奨 |
| 公式シラバスのURL: | https://certification.adobe.com/certification/project-manager-certified-professional/1320 |
Adobe AD0-E911 認定試験の出題範囲:
| トピック | 出題範囲 |
|---|---|
| トピック 1 |
|
| トピック 2 |
|
| トピック 3 |
|
参照:https://certification.adobe.com/certification/project-manager-certified-professional/1320
Adobe Workfront Project Manager Certified Professional 認定 AD0-E911 試験問題:
問題 #1
A project manager is assigned to a new Workfront request. The request specifies that the management team's sign-off is needed before the project can begin.
What is the appropriate action for the project manager to take?
A. Email the management team and request their approval.
B. Convert the issue into a project using a project template.
C. Use a customized approval process to route the issue for approval.
問題 #2
A project manager compares the original schedule for a task to another set of dates that moved later after predecessors slipped and the assignee changed a completion commitment.
What do these later, system-calculated dates represent?
A. They are Projected Dates that show the current forecast for task start and finish.
B. They are Milestone Path Dates that show when milestone tasks are expected to occur.
C. They are Planned Dates that show the originally scheduled task dates.
問題 #3
Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.
Why may this be the case?
A. The team needs to review the task before confirming the start date.
B. The primary task owner has time off logged in Workfront.
C. The task duration and planned hours are set to begin on Friday.
問題 #4
A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.
What steps should the project manager take to create a custom Workfront report with this information?
A. Visit the Reports page, create a new Project report, and add filters for Company ID and Group ID.
B. Visit the Reports page, create a new Project report, and add filters for Owner ID and Project Status.
C. Visit the Reports page, create a new Project report, and add filters for Company ID and Owner ID.
問題 #5
A project owner creates a project with the Schedule Mode set to Start Date.
Which task constraint is the default when creating new tasks in this scenario?
A. Must Start On
B. As Late As Possible
C. As Soon As Possible
解説:
| 問題 #1 正解: C | 問題 #2 正解: A | 問題 #3 正解: C | 問題 #4 正解: A | 問題 #5 正解: C |














800 お客様のコメント
品質保証JPexamはIT認定試験のシラバスに従って、試験問題の範囲を正確に絞って、的中率が99%の最新問題集を捧げます。
1年間の無料更新サービスJPexamは1年以内に問題集の無料更新サービスを提供し、お客様がいつでも最新版の問題集を持つことを保証いたします。もし試験の内容が変更されたら、弊社は直ちにお客様にお知らせします。それに、弊社の問題集が更新されたら、早速メールで最新バージョンを送付いたします。
全額返金JPexamの問題集を利用すると、短時間で勉強しても試験に合格できるのを保証いたします。試験に不合格になってしまった場合、弊社は全額返金いたします。(
ご購入前のお試しJPexamは問題集のサンプルを無料で提供いたします。ご購入前にサンプルを試用して製品の品質を確認することができます。ご遠慮なく利用してください。