Huawei HCIP-Data Center Facility Deployment V1.0 認定 H12-421 試験問題:
1. Check that the load switch is in the "OFF" position before powering up the URS5000.
A) True
B) False
2. In the process of disconnecting the battery pack switch, if there are multiple sets of batteries, first disconnect the main switch between the battery pack and the UPS, and then disconnect the switch of each battery pack.
A) True
B) False
3. In the process of using the battery, in order to reduce the deterioration of the voltage imbalance between the batteries, it is necessary to increase the charging voltage of the battery pack, and to activate and charge the battery to extend the battery life, which is called ().
A) Balanced charging
B) Floating charge
C) Charging test
D) Self-discharge
4. The UPS5000-E can press the battery cold start button on the bypass module without the main bypass input to start the inverter, and the system will automatically enter the battery inverter mode.
A) TRUE
B) FALSE
5. What may NetCol 5000-C insulation cotton damage result in?
A) Fan noise is too loud
B) The drainage capacity of the equipment is significantly reduced
C) Fan blocked
D) Pipeline condensation
質問と回答:
| 質問 # 1 正解: A | 質問 # 2 正解: A | 質問 # 3 正解: A | 質問 # 4 正解: A | 質問 # 5 正解: D |














841 お客様のコメント
品質保証JPexamはIT認定試験のシラバスに従って、試験問題の範囲を正確に絞って、的中率が99%の最新問題集を捧げます。
1年間の無料更新サービスJPexamは1年以内に問題集の無料更新サービスを提供し、お客様がいつでも最新版の問題集を持つことを保証いたします。もし試験の内容が変更されたら、弊社は直ちにお客様にお知らせします。それに、弊社の問題集が更新されたら、早速メールで最新バージョンを送付いたします。
全額返金JPexamの問題集を利用すると、短時間で勉強しても試験に合格できるのを保証いたします。試験に不合格になってしまった場合、弊社は全額返金いたします。(
ご購入前のお試しJPexamは問題集のサンプルを無料で提供いたします。ご購入前にサンプルを試用して製品の品質を確認することができます。ご遠慮なく利用してください。